- Soquel Canyon Parkway Pavement Rehabilitation
Project Description:
The work consists of, but is not limited to: mobilization; furnishing and installing video detection on existing traffic signals at intersections at Pinehurst Drive/Mindenvale Drive, Cypress Point Drive/Elinvar Drive, and Slate Drive; traffic control, cold milling of existing AC pavement; AC overlay; upgrading existing P.C.C. access ramps where needed to comply with current ADA standards; adjustment of valves and manholes to grade; inclusion of buffered bikeways where feasible, and roadway pavement signing and striping.
Location:
Soquel Canyon Parkway from Pipeline Avenue to Pomona Rincon Road
Current Construction Activities:
Work has been completed on the installation of video detection. Concrete work began in January and pavement work will be done in February.
Construction Timeframe:
60 working days
Project Contact:
Carl Hassel, Sr. Engineer
Phone: 909-364-2817