The work comprises but is not limited to: Mobilization; Traffic Control; selective 2-inch grind and 2-inch AC overlay; ADA Ramps, adjustment of existing manholes to grade; adjustment of water valve can covers; storm drain culvert replacement (2) regrading of shoulders and placement of compacted base material, and restoration of striping, pavement markings, and legends.
Woodview Road between Peyton Drive and 2000' West of Pipeline Avenue.
Current Construction Activities:
The bid was opened on July 14, 2022, and the project was awarded to Gentry Brother's Inc on September 13, 2022. Work is anticipated to begin in February 2023 and will be completed in May 2023.
35 working days
Project Contact:
Carl Hassel, Engineering Manager
Phone: (909) 364-2817
Email: chassel@chinohills.org