Grand Avenue Pavement Rehabilitation Project

Project Description:

Mobilization; Traffic Control; removal and reconstruction of deteriorated pavement, 2-inches grind and overlay asphalt pavement; reconstruction of access ramps; adjustment of water valves, sewer manholes and utility covers; installation of video detection; and restoration of striping, pavement markings, and legends. Work will be required to be performed at night.

Location:

Grand Avenue from Peyton Drive to State Route 71.

Current Construction Activities:

This project is currently out to bid. The bid opening date is May 20, 2021. The anticipated award date is June 22, 2021.

Construction Timeframe: 

30 working days

Point of Contact:

Carl Hassel, Sr. Engineer
Phone: 909-364-2817
Email: chassel@chinohills.org