- Home
- About Us
- Major Construction
- 1,2,3 TCP Removal Treatment Plant
The work comprises the following: mobilization, demolition, trees removal, grading and earthwork, piping, instrumentation, Booster 9 improvements (such as replacing pumps and motors, upgrading electrical units and telemetry system), landscaping, block wall, installing GAC treatment vessels, surge tank, connections to existing utility mainlines, start-up and commissioning, and other appurtenances to complete the project.
3982 Eucalyptus Avenue, Chino Hills (See attached Project Location Map)
Below are the construction key milestones/ schedule:
Construction Timeframe:
375 calendar days
(Note: Working Hours are from 7:00 am - 7:00 pm, M-F, except City Holidays)
Point of Contact:
Fe Rama, P.E., Senior Engineer
Phone: (909) 364-2776 mailto:frama@chinohills.org
Email: frama@chinohills.org