Fairfield Ranch Road Pavement Rehabilitation

City staff evaluated existing road conditions using the 2021 Pavement Management System Report, which includes a Pavement Condition Index (PCI) analysis and field investigations. Based on these evaluations, the City has selected Fairfield Ranch Road for street rehabilitation.

Project Description

The Work comprises, but is not limited to: mobilization; traffic control; grind existing pavement up to 4 inches; install AC Overlay up to 4 inches thick; reconstruct ADA Access Ramps; adjust utility covers and valve lids to finished grade; reconstruct concrete sidewalk; reconstruct curb and gutter; restore striping, pavement legends, and pavement markers.

Location

The project work area includes work along Fairfield Ranch Road between Monte Vista Avenue and Soquel Canyon Parkway.

Construction Activity

The bid opening is scheduled for November 13, 2025, with the anticipated contract award in December 2025. Construction is expected to commence in early spring 2026. 

Construction Timeframe

30 Working days.

Point of Contact:

Victor Yanez, P.E., Senior Engineer
Phone: (909) 364-2755
Email: vyanez@chinohills.org